Project Implementation Collateral: Gorontalo Regional Government Claims 8 Companies Reach IDR 3 Billion
As of January 5, 2023, the Regional Government of Gorontalo Regency has made a claim to many insurance companies through the Office of Public Works and Spatial Planning (PU-PR).
A total of IDR 3 billion, or IDR 3,055,196,676, was claimed in implementation guarantee claims.
This is an extension of the 14 businesses' defaults on crucial road infrastructure development projects for the years 2021–2022.
The sum of IDR 3 billion from implementation guarantee claims is just an accumulation of a total of 8 enterprises, according to data that the Chronologi.id editor has received.
Supriyanto Ali, the head of the PU-PR Service's Bina Marga Division, stated that the service provider's inability to complete the task was the reason for the demand for implementation assurances. The government must submit a performance guarantee claim letter to the insurer no later than 30 days after the contract has been terminated, whichever comes first.
"Only 8 businesses (out of 14 businesses) handled the claims related to the implementation guarantee. In a special interview with Chronologi.id on Monday, 30 January 2023, Ali stated, "I have issued a claim form to 3 insurance parties that guarantee 8 jobs.
Each implementation guarantee has a slightly different value. For instance, the business CV Adhi Perkasa Utama's guarantee for the completion of Jalan Tunggulo - Yosonegoro is Rp. 113,720,103, which is a percentage of the budget contract value of Rp. 2,274,402,067. PT Jamkrindo Syariah is the garant for the execution of this work.
Four more projects, including the CV Rikza Mulia Abadi-owned Jalan Abdul Rahman Moito - Dutulanaa project, are also guaranteed to be completed by PT Jamkrindo Syariah. The overall guarantee for carrying out this job is Rp 360,012,905, which is equal to 7.2 billion rupiah, or Rp 7,200,258,084 in contract value.
Then, CV Asrindo Putra Mandiri is responsible for the work on Jalan Sukamakmur-Polohungo. The implementation guarantee for PT Jamkrindo Syariah on this project is Rp 311,910,603 out of the total budget contract of Rp 6,238,212,069, or Rp 6.2 billion.
Additionally, the Jalan AK project is guaranteed by PT Jamkrindo Syariah. Luneto - Ombulo is a property of CV Bangun Jaya. Out of a total budget of Rp 7,987,343,188, or Rp 7.9 billion, there is a guarantee for the execution of this job in the amount of Rp 399,367,159. So CV Artha Graha Karya is the rightful owner of the Musa Kaluku-Bulila road repair project. Out of a contract worth Rp 6,450,001,197, or Rp 6.4 billion, Rp 322,500,059 is the guarantee for carrying out this work.
In contrast to other service providers, according to Ali, PT Asuransi Asei is providing the guarantee for the execution of CV Bintang Gani's Buhu-Iloponu-Perintis Road Improvement Project. The guarantee for carrying out this job has a value of Rp 229,731,636 out of a budget contract of Rp 4,594,632,772 or Rp 4.5 billion.
"Including the work on PT Bima Panca Karya's Jalan Raja Wadipalapa-Bulila. With PT Asuransi Asei, their performance guarantee is registered. From a budget contract of IDR 16,976,606,785 or IDR 16.9 billion, the total guarantee is IDR 848 million or IDR 848,830,339, according to Ali.
The guarantee for the implementation of the work on Jalan Sama'un Pulubuhu - Bolihuangga, owned by the business CV Kifas Pratama Jaya, is provided by PT Asuransi Jasaraharja Putera. The budget is IDR 9,382,477,441 or IDR 9.3 billion, leaving a total guarantee of IDR 469,123,872 available.
Regarding the issue of guarantee claims for the execution of the remaining 6 projects, Ali opted not to elaborate. He only affirmed that the insurer had responded to the performance guarantee claims made by the 8 firms.
Only the guarantee claims for the execution of 8 companies are under my purview. Thank goodness the insurance has also approved the letter of claim. About Rp 3 billion worth of total guarantee claims had been made in total for the implementation of 8 enterprises, Ali said.